6/02/2012

MSM8660 3D UI PowerLift Power Measurement Procedure

1. After loading MSM build, load device QCN, place in airplane mode before measurements.
2. Request for the PowerLift application from QCT side(A200_ANDROID_PowerLift_8660)
3. Double click on "install.bat" of the provided package to install PowerLift application
4. Reboot the device
5. Make sure Display Timeout is set to 30 minutes
6. Run graphics under e.g. Main menu > select PowerLift
7. Start power measurement

Note:
1. Graphic test case(QGC23) is measured with LCD/BL ON with default setting values. LCD/BL power contribution should be subtracted after power measurement
2. To verify the FPS of PowerLift, this can be seen from the PowerLift application UI